Wednesday, June 9, 2010

Day 3 of LBA build - progress report

Here is the updated completion map for the LOFAR LBA antenna installation.



Today's progress is marked in blue.

-- 3 aerials were completed prior to this week (red + orange)
-- 22 aerials were completed on Monday 7th (yellow)
-- 30 aerials were completed on Tuesday 8th (green)
-- 34 aerials were completed on Wednesday 9th (blue)

Thanks go to everyone who participated. The crew continues tomorrow morning for the final 7 antennas as well as a lot of labelling and consolidating!