![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjuIUw2OusmYEkqxUILfNqluyHeOuUCzaacT5jkfGwbCDYzivFQE-gETJo9Ct90wms0jgbj91DMZZxE1Yosn1kCN6CRt51XggZgnvbZmphtRvsSBJSrh0Jp10TrjSBFTY-MqV5T4Sv76Z1G/s400/hba_progress_100708.jpg)
The current status is:
-- 13 tiles were installed on Friday 2nd (red)
-- 14 tiles were installed on Monday 5th (orange)
-- 18 tiles were installed on Tuesday 6th (yellow)
-- 8 tiles were installed on Wednesday 7th (light green)
-- 10 tiles were installed on Thursday 8th (dark green)
Tiles #93 and #94 were difficult to place owing to the proximity of a steep edging bank.
Today they have also done some work around the RF-cabin to improve the pedestrian access and the LBA field has now been completely cleared of left over building materials from its installation work.
No comments:
Post a Comment