HBA progress - 45 tiles installed.

Here is the updated completion map for the LOFAR-Chilbolton HBA antenna installation. Today's progress is marked in yellow.



The current status is:

-- 13 tiles were installed on Friday 2nd (red)
-- 14 tiles were installed on Monday 5th (orange)
-- 18 tiles were installed on Tuesday 6th (yellow)


HBA tile #0 has been hatched to indicate that problems have been discovered and there is rework that needs to be done. This particular tile should not be considered complete just yet.