Using an all-terrain forklift, the pallets are removed from the lorries.

In addition to the tiles themselves, there are stacks of "lids" which will go on top of each tile after it is unfolded.

The slowly building stock of HBA tiles.


A confirmation phone call from the installation company (Autonational) has confirmed that their engineers are in the area and will be on site at the crack of dawn. Also, the first delivery is now due earlier than expected. Then, to make matters worse, it seems that some of the work that should have been completed by Friday remains undone.